Projected capital requirement
The investment presentation states a total net capital requirement of €5.85 million for all phases, external works and fit-out.
Sponsor projections for capital expenditure, occupancy, revenue and asset value—presented transparently and without implying certainty.
The investment presentation states a total net capital requirement of €5.85 million for all phases, external works and fit-out.
The sponsor states that this amount has already been invested in the completed basement for Phase 1.
| Investment item | Net amount |
|---|---|
| Phase 1 “Stadl” construction | €1,970,000 |
| Chalets, phases 2–4 | €2,950,000 |
| External works, site protection and refurbishment | €700,000 |
| Interior fit-out and furnishings | €570,000 |
| Total projected net investment | €5,850,000 |
The sponsor presentation models 350 operating days per year at an average bed price of €75, with occupancy rising from 55% to 75%.
The €8.4 million value is a sponsor projection. An independent valuation should test methodology, completion assumptions, stabilised net operating income, market yields and title/security position.